Launceston road repairs schedule revealed

I'm delighted to have been sent the provisional dates for the re-surfacing works around Launceston. A huge number of local residents have complained about the state of our streets. The potholes cause damage to cars and increase the risk of accidents.

Over the past three years, millions of pounds has been stripped out of the council's fund for road repairs and safety as the Conservatives and Independents have taken the money to plug other holes in their budget - mainly their disastrous car parking policy.

But the new budget, proposed by the Liberal Democrats and accepted by the majority of councillors, has an extra £2.5 million over the next two years to repair our roads. If the Independents, Labour and Conservative Leader of the council had their way, we would not be spending this money repairing our roads and the state of them would just be getting worse and worse.

The roads that are on the provisional schedule for re-surfacing are:

  • Western Road at the junction with Pennygillam roundabout - work commences 8th July for two nights;
  • St Johns Road - work commences 12th August for between three and five days;
  • St Thomas Road and Newport Square - work commences 7th October for up to 12 nights

Also on the list for work this year is Tredydan Road, but no date has been fixed for this yet.

As mentioned above, these are provisional dates. If there are emergencies in other parts of Cornwall (such as the Looe landslips) then these may be delayed. Equally, I will be pressing for work to be brought forward if at all possible. The constraints at this time are less about money and more about the people and equipment needed to do the job.

In the meantime, highway engineers will be filling individual potholes as quickly as possible. If you know of a pothole near you, please get in touch. Huge thanks to all the officers who have surveyed the roads and put together the schedule.